Selfridges, Birmingham

  • Selfridges Birmingham Elevator Area
  • Selfridges Entrance Door Curtain
  • Selfridges Click and Collect Point
  • Selfridges Outside View
  • Selfridges Shop Floor

About This Project

Selfridges, Bullring Birmingham City Centre (Level 2)

The Level 2 works included the following:

  • Modification of existing HVAC, Public Health and also BMS services.
  • Provision of new HVAC and Public Health services to various concessions throughout this level.

 

Selfridges, Bullring Birmingham  City Centre (Level 3)

The Level 3 works included the following:

  • Modified existing HVAC, Public Health and also BMS services.
  • Provision of new Ventilation to the Beauty Rooms and Starbucks Coffee Shop
  • Provision of new HVAC and Public Health services to various concessions throughout this level.
  • Provision of new HVAC services and door curtain to Click & Collect Area of the store

 

Project Duration Level 3

August 2013 – June 2015

Project Duration Level 2

January 2014 – December 2014

Project Value Level 3

£320,000

Project Value Level 2

£75,000

Category
Mechanical Works
Tags
mechanicalworks